Bill of Quantities Construction Guide for Australian Projects

Bill of quantities construction: blueprints, calculator and spreadsheet on a quantity surveyor's desk at a house construction site

A bill of quantities (BOQ) is a tender and cost-control document that lists every measured item of work in a building project. Items sit in trade groups. Each one carries a unit and a quantity, ready for pricing. In Australian bill of quantities construction practice, a quantity surveyor (QS) measures the work to the Australian Standard Method of Measurement (ASMM).

Key Takeaways

  • A BOQ converts drawings and specifications into numbered, measured items so every tenderer prices identical scope.
  • Australian BOQs follow the ASMM, published by the Australian Institute of Quantity Surveyors (AIQS) and Master Builders Australia.
  • Enter BOQ rates exclusive of Goods and Services Tax (GST), then add the 10% GST in a separate column.
  • Excel handles small residential BOQs, while CostX and Buildsoft Cubit suit larger or drawing-heavy projects.
  • Owner builders use a BOQ for material ordering, comparable trade quotes and lender cost reports.
  • No verified figure is available for Australian BOQ fees, so request at least three written quotes.

What Is a Bill of Quantities in Construction?

A bill of quantities in construction is a structured schedule that describes, measures and numbers every work item in a project, so builders apply their own unit rates and return tenders that an owner compares line by line. The QS prepares the BOQ from the drawings and specification before tendering starts. Pricing comes later.

A BOQ separates quantity from price. The QS decides how much work the project contains, while each tenderer decides on their own what that work will cost.

That split strips out the guesswork behind wildly different quotes from builders who’ve all read the same set of plans. Picture a supermarket list sorted by aisle. Every builder shops from that one list, so any gap between the totals comes down to price, not scope.

Each BOQ line holds six pieces of information: an item number, a written description, a unit of measurement, a measured quantity, a unit rate and an extended amount. The maths is simple. Quantity times rate gives the amount.

You’ll see BOQs on Australian commercial buildings, multi-residential developments, government projects and custom homes. Volume home builders are different. Their in-house estimating systems take the place of a formal BOQ, though those systems still run on exactly the same quantity takeoff principles.

Sections a BOQ Includes

House BOQs follow construction order. A typical Australian one groups the work into trade sections, starting at preliminaries and finishing with allowances for PC items and provisional sums. This table shows what each standard section covers and the unit it’s usually measured in.

Section What It Covers Typical Unit
Preliminaries Site setup, insurances, supervision, temporary services item
Site Preparation Clearing, excavation, fill, compaction m³ / m²
Concrete Footings, slabs, edge beams, reinforcement m³ / t
Masonry Brick veneer, blockwork, lintels m² / no.
Carpentry Wall frames, roof trusses, fix-out m² / lm / no.
Roofing and Drainage Roof cover, gutters, downpipes m² / lm / no.
Finishes Plasterboard, tiling, painting m²
Services Electrical, plumbing, mechanical item / no.
External Works Driveways, paths, fencing m² / lm
Allowances PC items and provisional sums item

Who Prepares a Bill of Quantities in Australia?

A quantity surveyor prepares a bill of quantities in Australia, usually engaged by the owner, architect or builder, and trained to measure construction work under the ASMM and price it against current market rates. Other people produce BOQs too. Estimators inside building companies write them for their own tenders, and experienced owner builders put together simple ones for single dwellings.

An owner’s QS checks that the builder’s price is fair. On the other side, a builder’s estimator uses the BOQ to win work, and the goal there is a price that stays profitable. The rules match. The interests don’t.

Plenty of QS firms work beyond the BOQ. During design they prepare cost plans, and during construction they issue progress reports for lenders. Tax depreciation schedules come after completion, so one firm can follow a project from concept all the way to handover.

Does the Quantity Surveyor Need AIQS Membership?

No. Quantity surveying isn’t a state-licensed occupation in Australia the way building work is, which leaves AIQS membership entirely voluntary for practising surveyors.

That said, membership carries real weight. Every member commits to the institute’s code of ethics and continuing professional development, and the AIQS awards a Certified Quantity Surveyor (CQS) designation to members who meet its competency requirements.

Check a surveyor’s membership directly with the AIQS before you sign a fee proposal. Then ask for professional indemnity insurance details. A single measurement error flows straight into every tender price, and that’s exactly the kind of mistake the cover is there for.

What Measurement Standard Do Australian BOQs Use?

Australian BOQs use the Australian Standard Method of Measurement of Building Works, known as the ASMM, which sets rules for how each trade is measured, described and grouped so every QS and tenderer reads quantities the same way. Two bodies stand behind it. The AIQS and Master Builders Australia publish the ASMM together.

Don’t let the name mislead you. Despite the word “Standard” in its title, the ASMM is an industry publication rather than a document issued by Standards Australia.

Net measurement is the key ASMM principle. Work gets measured as fixed in its final position, with the waste allowance built into the unit rate rather than added to the quantity. Laps and offcuts go there too.

Tenderers price against these rules. So if a QS measures brickwork gross instead of net, every bricklayer’s rate ends up wrong for that particular BOQ, because each rate already assumes net quantities.

How ASMM Differs from UK NRM2

Use the ASMM for Australian projects. The Royal Institution of Chartered Surveyors (RICS) New Rules of Measurement 2 (NRM2) suits UK work and international projects that follow British practice.

This table sets the two measurement standards side by side, from publisher through to contract fit.

Feature ASMM NRM2
Publisher AIQS and Master Builders Australia RICS
Jurisdiction Australia United Kingdom
Units Metric Metric
Typical Contracts AS 4000, AS 2124 JCT, NEC
Best Use Australian tenders UK and British-style tenders

Bill of Quantities Construction Format and Structure

A standard bill of quantities construction format splits the project into preliminaries, trade sections and allowances, then lists each item with a reference number, description, unit, quantity, unit rate and extended amount, ending in a summary page that carries every trade total to one tender figure.

Number every item by section and line. The first concrete item, for example, becomes 3.01. With that system in place, tenderers and the QS can point to exact lines during queries, and the contract administrator can do the same when claims arrive.

Preliminaries

Preliminaries cover site costs that don’t belong to any single trade. The list runs long. Site establishment, temporary fencing, site sheds, toilets, scaffolding, waste removal and supervision all sit here, along with insurances such as contract works and public liability.

On residential jobs, home warranty insurance joins the list wherever state law requires it. Pricing splits two ways. Time-related preliminaries such as supervision get priced per week, while fixed items like site establishment go in as a single item.

Trade Sections

Trade sections follow the order of construction, running from earthworks right through to painting and the external works that finish the job. Each one closes with a subtotal. That figure carries to the summary page.

Descriptions here must reflect Australian requirements. The National Construction Code (NCC) sets performance requirements, while AS 3959 governs construction in bushfire-prone areas through Bushfire Attack Level (BAL) ratings. AS 4055 sets wind classifications for housing, and termite management falls under AS 3660.

Location reshapes the scope. Either a BAL-29 site in the Adelaide Hills or a cyclonic wind classification in Townsville will change the window and cladding items, and the roof fixing items change with them. The BOQ has to name those requirements, or tenderers can’t price compliant products.

Measurement Units and Descriptions

Australian BOQs are metric across every trade. This table lists each unit alongside its typical uses, with the imperial equivalent added for anyone who still thinks in feet and pounds.

Unit Abbreviation Used For Imperial Equivalent
Lineal metre lm Gutters, skirting, edge beams 1 lm = 3.28 ft
Square metre m² Walls, floors, roofing 1 m² = 10.76 sq ft
Cubic metre m³ Concrete, excavation, fill 1 m³ = 35.31 cu ft
Tonne t Reinforcement steel 1 t = 2,205 lb
Number no. Doors, fixtures, downpipes N/A
Item item Lump sums, preliminaries N/A

A clear description reads like an instruction: “Brick veneer, 230 × 110 × 76 mm clay bricks, stretcher bond, raked joints, measured net.” Vague entries cost money. Write just “brickwork” and five tenderers will price five different products.

What Are Provisional Sums and Prime Cost Items?

Prime cost (PC) items are allowances for materials or fittings the owner has not yet selected, such as tapware or appliances, while provisional sums are allowances for work that cannot yet be measured, such as rock excavation; both are adjusted to actual cost later.

PC items normally cover supply only, which means the installation is priced as a separate line somewhere else in the BOQ. Provisional sums are different. They usually take in supply and installation together.

This table sets PC items against provisional sums, from scope through to how each is adjusted.

Feature Prime Cost Item Provisional Sum
Covers Unselected materials or fittings Work not yet measurable
Includes Labour Usually no Yes
Example Oven, cooktop, tapware Rock excavation, retaining walls
Adjustment Actual price vs allowance Actual cost vs allowance
Margin As stated in contract As stated in contract

In New South Wales and Victoria, state home building laws regulate how PC items and provisional sums appear in residential contracts, and Queensland’s law does the same. Rules change. Check the current version with your state regulator before you finalise residential allowances.

Keep allowances realistic. A lowball PC allowance makes a tender look cheap, then turns into a cost overrun once the owner selects the actual fittings.

How Are PC Sums Adjusted at Handover?

PC sums get adjusted once the item is bought or the work is finished, and the final claim confirms every adjustment. Follow this sequence:

  1. Record the actual invoiced cost of the selected item or completed work.
  2. Subtract the allowance in the BOQ from the actual cost.
  3. Apply the builder’s margin to the difference if the contract allows it.
  4. Add the result to the next progress claim as a credit or debit.
  5. Reconcile every allowance in the final claim at practical completion.

How to Prepare a BOQ Step by Step

Prepare a BOQ by gathering complete drawings and specifications, setting up a trade breakdown, measuring each item to ASMM rules, writing clear descriptions, adding preliminaries and allowances, checking the quantities, and then pricing each line with current unit rates, builder’s margin and GST.

Scale doesn’t change the process. Quantity takeoff follows the same order whether the job is a granny flat out the back or a full hospital project.

  1. Gather the full architectural set, structural engineering drawings, specification, soil report and energy efficiency report.
  2. Set up a trade breakdown that matches the construction sequence and the ASMM section order.
  3. Measure each item net as fixed, using the unit the ASMM sets for that trade.
  4. Write item descriptions that state material, size, finish, fixing method and any relevant Australian Standard.
  5. Add preliminaries, PC items, provisional sums and a contingency line for the owner’s budget.
  6. Check quantities with a second method, such as comparing measured floor area against the drawing schedule.
  7. Price each line using supplier quotes, subcontractor quotes or a published cost guide.
  8. Apply builder’s margin, calculate GST at 10% and carry every trade subtotal to the summary page.

Write every assumption onto the BOQ itself. A note such as “slab thickness assumed 100 mm pending engineering” tells every tenderer exactly where the risk sits before a single rate goes in.

Bill of Quantities for Building Construction Excel Template

A bill of quantities for building construction Excel template is a spreadsheet with fixed columns for item number, description, unit, quantity, unit rate, amount and GST, where formulas multiply quantity by rate and roll trade subtotals into a summary sheet. Excel suits single dwellings and granny flats. Renovations work well in it too.

Yes, a full residential BOQ fits in Microsoft Excel. The catch is takeoff. Excel has no drawing takeoff tools, so you’ll measure from PDF drawings with a scale ruler or a PDF measuring tool and key the quantities in by hand.

Give each trade its own worksheet. Add a summary sheet and a rates sheet alongside them, then record the source and date of every rate on that rates sheet so anyone can trace where each number came from.

Columns a BOQ Spreadsheet Should Have

Eight columns cover it. That’s enough for a BOQ spreadsheet to calculate both ex-GST and GST-inclusive amounts without any separate working on another sheet. This table gives each column’s heading and its content or formula, with row 2 as the first item row.

Column Heading Content or Formula
A Item No. Section and line, e.g. 3.01
B Description Material, size, finish, standard
C Unit m², m³, lm, t, no., item
D Quantity Measured net quantity
E Rate ex GST ($) Unit rate in AUD
F Amount ex GST ($) =D2*E2
G GST ($) =F2*0.1
H Amount inc GST ($) =F2+G2

Lock the formula cells against accidental overwrites. Data validation on column C is worth setting up too, since it forces every unit typed into that column to match the ASMM list.

Give PC items and provisional sums their own sheet. Adjustments get easier. With allowances kept apart from the measured trades, every change that comes up during construction is quick to find and simple to reconcile.

Worked Example for a Single-Storey House

The example house is a hypothetical single-storey brick veneer home on a concrete slab, 15 m × 10 m (49 ft × 33 ft) in plan. That’s a 150 m² (1,615 sq ft) footprint. Ceilings sit at 2.4 m (about 7 ft 10 in), and a gable roof carries gutters along the two long sides.

These dimensions are illustrative only. On a real job, a structural engineer sets the actual slab and footing design, so don’t copy these figures onto your own drawings.

The quantities work out as follows:

  1. Calculate the slab volume: 15 m × 10 m × 0.1 m = 15 m³.
  2. Calculate the edge beam volume: 50 lm perimeter × 0.3 m wide × 0.45 m deep below slab = 6.75 m³.
  3. Calculate the gross external wall area: 50 lm × 2.4 m = 120 m².
  4. Deduct an assumed 20 m² of window and door openings to give 100 m² of net brick veneer.
  5. Measure the gutters: 2 sides × 15 m = 30 lm.

This table shows the resulting BOQ lines with metric and imperial quantities.

Item No. Description Unit Quantity (Metric) Quantity (Imperial)
3.01 Concrete slab, 100 mm (4 in) thick m³ 15.00 530 cu ft
3.02 Edge beams, 300 × 450 mm m³ 6.75 238 cu ft
3.03 Vapour barrier under slab m² 150.00 1,615 sq ft
5.01 Brick veneer, measured net m² 100.00 1,076 sq ft
9.01 Quad gutter, 115 mm lm 30.00 98 ft
9.02 Downpipes, 90 mm no. 4 N/A

Unit rates are left out on purpose. No verified current prices were supplied for this example. Enter these rows into a bill of quantity for building construction Excel file, add a rate in column E, and each line completes itself automatically.

Excel vs CostX vs Cubit

Excel wins on small, low-budget residential jobs. Larger drawing sets and frequent revisions tip the balance toward CostX and Buildsoft Cubit, and so does the arrival of Building Information Modelling (BIM) models.

This table shows where each tool fits best and how it handles drawing takeoff.

Tool Best For Takeoff from Drawings Australian Connection
Microsoft Excel Owner builders, small jobs No, manual entry General software, used everywhere
RIB CostX QS firms, BIM projects Yes, 2D and 3D Originally developed by Exactal
Buildsoft Cubit Builders and estimators Yes, 2D and BIM Australian-developed

How Long Does a BOQ Take to Prepare?

Preparation time for a BOQ depends on project size, drawing completeness, the number of trades and how many design changes arrive during measurement, and no verified figure is available for typical Australian turnaround times, so ask each QS for a written timeframe.

Drawing quality drives timing more than anything. Incomplete sets push the QS into writing assumptions and provisional sums, and every revision that lands afterwards means remeasuring the affected items.

File format matters too. Native CAD files and BIM models speed up digital takeoff, while scanned paper drawings slow measurement down because software can’t read scale or layers from them.

How Much Does a Bill of Quantities Cost in Australia?

The cost of a bill of quantities in Australia varies with project size, complexity, location and the level of detail requested, and no verified figure is available for this guide, so request at least three written fee proposals from quantity surveyors before engaging one.

Judge proposals on scope. Price alone tells you little, because one proposal may include trade-by-trade pricing while another delivers nothing beyond the measured quantities.

What Affects Quantity Surveyor Fees

Fee drivers repeat. The same handful of factors shape quantity surveyor fees on every project, regardless of its size or the type of building involved. This table lists each factor and its effect on the fee.

Factor Effect on Fee
Project size More items raise the fee
Drawing quality Incomplete drawings add assumptions and time
Number of trades More trades mean more measurement
Report type Full BOQ costs more than an estimate
Site location Regional sites may add travel
Turnaround Urgent deadlines can raise the fee
Revisions Design changes trigger remeasurement

Does an Owner Builder Need a Bill of Quantities?

No, a BOQ is not a general legal requirement for owner builders in Australia, but a BOQ makes trade quotes comparable, prevents ordering errors and supports a construction loan application, so most owner builders gain from one even on a single house.

State regulators issue owner builder permits, with NSW Fair Trading and the Queensland Building and Construction Commission (QBCC) as two examples. Conditions vary. Check yours with the regulator in your state.

An owner builder acts as project manager, which turns the BOQ into the ordering list and the quote request at once. One document, two jobs. A bill of quantities for building construction on a single dwelling lets you send each trade section to two or three subcontractors and compare like with like.

Gaps show up too. If no trade has priced the waterproofing membrane in the bathroom, the missing line shows up on paper before any work starts on site.

Do Banks Ask Owner Builders for a BOQ?

Yes, many lenders ask owner builders for an independent QS cost report or BOQ before they’ll approve a construction loan. Funds come out in stages. The usual sequence runs base, frame, lock-up, fixing and completion.

A QS report shows the lender that the budget stretches across every one of those stages, from the base right through to completion. Policies differ. Confirm the exact report your lender wants before you order one.

When to Hire a QS or Build Your Own BOQ

Hire a QS whenever a lender or contract demands independent figures, and do the same on any complex site where measurement errors would get expensive. Small jobs are different. If the project is simple and self-funded, build your own BOQ.

This table matches common owner builder situations to the better option.

Situation Best Option Reason
Lender requires a cost report Hire a QS Lenders want independent figures
Sloping or rocky site Hire a QS Earthworks risk needs expert measurement
Bushfire or cyclone region Hire a QS Compliance items affect many trades
Small shed or garage Build your own Few trades, simple quantities
Self-funded renovation Build your own Excel template handles the scope

Is a Bill of Quantities a Contract Document?

Yes, on Australian projects a bill of quantities becomes a contract document when the contract lists it among the contract documents; otherwise it stays a tender aid, and the lump sum price, drawings and specification govern the scope of work.

Most of Australia’s residential building contracts, HIA and Master Builders forms included, are lump sum contracts based on plans and specifications. BOQs rarely make it into them.

That changes on commercial jobs. Government and commercial projects use BOQs as contract documents more often, and under contracts based on AS 4000 the list of contract documents decides whether the BOQ binds the parties.

Who Carries Quantity Risk Under the Contract?

When the BOQ is a contract document, the principal carries quantity risk. Otherwise it’s on the contractor. A BOQ issued purely as a tender aid leaves every quantity error sitting with the contractor who priced the work from it.

This table compares the two arrangements on risk and error correction.

Contract Arrangement Quantity Risk Error Correction
BOQ is a contract document Principal Errors valued as variations
BOQ is a tender aid only Contractor No adjustment for quantity errors

Read the BOQ clause before pricing, along with the order of precedence clause that ranks the contract documents against each other. They settle who pays for missed items.

How Bills of Quantity in Construction Drive Tenders and Claims

Bills of quantity in construction drive the full contract lifecycle on Australian projects because the same measured items that tenderers price also become the basis for valuing progress claims, pricing variations and reconciling prime cost and provisional sums at practical completion.

Tendering

Issue the BOQ with the tender documents so every tenderer prices identical quantities. Assessment gets easier. The tender assessor then compares rates line by line across every submission, and that side-by-side view is where unbalanced pricing shows up.

Unbalanced pricing happens when a tenderer loads rates onto early items to improve cash flow, banking more money in the opening stages of the job. A line-by-line comparison catches it fast.

Progress Claims and Variations

Value each progress claim by applying the percentage complete to every priced BOQ line, so the claim tracks the work actually in place. Take the slab. Once it’s fully poured, items 3.01 to 3.03 are claimed at 100%.

Where the work is similar, price variations at the existing BOQ rates. Payment claims follow state law. Each state’s security of payment legislation sets the process, and a priced BOQ gives both parties a clear basis for valuing those claims.

BOQ vs Cost Estimate vs Schedule of Rates

A BOQ is more accurate than a cost estimate for tendering because it measures every item from completed drawings, while a cost estimate relies on rates per square metre or elemental allowances, and a schedule of rates lists unit prices without fixed quantities.

This table compares five common costing documents across purpose, author, accuracy and pricing.

Document Main Purpose Prepared By Accuracy Includes Prices
Bill of Quantities Tendering and contract control Quantity surveyor High Yes, once priced
Cost Estimate Early budget check QS or builder Low to moderate Yes
Cost Plan Budget control during design Quantity surveyor Moderate Yes
Schedule of Rates Pricing unmeasured work Contractor or QS Depends on quantities Rates only
Bill of Materials Ordering supplies Builder or supplier High for materials Sometimes

Match the document to the design stage. A cost estimate fits the concept phase, and a cost plan takes over while the design develops and the budget needs tighter control. Once drawings are complete, switch to a BOQ. Schedules of rates sit apart from that sequence, since they suit maintenance and repair contracts where quantities stay unknown.

Frequently Asked Questions

Is GST Included in a Bill of Quantities?

No. Australian BOQ rates are normally entered exclusive of GST, and the 10% tax is calculated in a separate column before it’s shown in the tender total.

What Units Does an Australian BOQ Use?

Australian BOQs use metric units. Lengths go in lineal metres, areas in square metres and volumes in cubic metres, while reinforcement is measured in tonnes and counted elements or lump sums appear as “no.” or “item”.

Can BIM Produce a Bill of Quantities?

Yes. BIM software extracts quantities directly from a 3D model, and tools such as CostX link those quantities to rates in a process called 5D costing. A QS still checks the output.

Does the National Construction Code Affect a BOQ?

Yes. The NCC sets requirements for structure, fire safety, energy efficiency and waterproofing, so BOQ item descriptions must specify compliant products such as rated insulation and wet-area membranes. Generic entries won’t do.

Where Can I Find Current Unit Rates in Australia?

Request supplier and subcontractor quotes for live pricing. Then cross-check those quotes against a published cost guide such as the Rawlinsons Australian Construction Handbook, so every rate has a second reference point before it goes into the BOQ.

Conclusion

Bill of quantities construction work in Australia is shifting from manual takeoff toward model-based measurement. Speed has changed. BIM models, paired with tools such as CostX and Cubit, now generate quantities that once took days of scale-ruler work.

The fundamentals haven’t moved. Measurement follows the ASMM, and rates sit ex-GST. Owners also need clear allowances for PC items and provisional sums, exactly as they did before any software arrived.

Owner builders who learn to read and build a BOQ today will brief QS firms more clearly and compare trade quotes faster, which also helps when a lender asks for a cost report. Start small. Open an Excel template on your next project and measure one trade carefully, then expand from there.

Rachel Park

Rachel Park leads sustainability, roofing, and building materials content at Constructionspedia, drawing on over 10 years of commercial and residential construction experience. She holds an M.S. in Sustainable Building Systems from UC Berkeley and is a LEED AP BD+C, specializing in roofing systems, insulation, waterproofing, and energy-efficient materials. Her research-backed guides help homeowners and industry professionals make informed decisions about construction and green building.